| II
|
Forgings / Fabricated Items |
Action By |
| |
|
|
| 1.
|
a.
|
Transfer code no. of pipes on each part
pcs of the particular length of pipe to be used for
fabricated pipes, tees and plain forgings. |
Sub
Contractor |
| |
b.
|
Fill the pipe code stamp transfer report
accordingly. |
Sub
Contractor |
| |
|
|
| |
PN – XXX Within 300 mm from fixed flange
for lined pipe. |
|
| |
For
Elbow at center |
|
| |
For
Tee at center |
|
| |
For
Reducer at Ľ of the length |
|
| |
|
|
| 2
|
Punch Lot No. on the plain forgings.
Re-punch pipe code no. if it is distorted during
forging. |
|
| |
|
|
| |
F XXX PN - XXX |
|
| |
|
|
| 3
|
Punch Identification No. on the fabricated
items as follows |
Sub
Contractor |
| |
|
|
| |
For
Pipe |
-
|
At
O.D. surface of fixed flange after Lot No./ Machinist /
Flange Inspector’s punch |
|
| |
For
Tee |
-
|
At
O.D. surface of TCF and BCF after Lot No. / Machinist /
Flange Inspector’s punch |
|
| |
For
Elbow |
-
|
At
O.D. surface of fixed flange after Lot No. / Machinist /
Flange Inspector’s punch |
|
| |
For
Reducer |
-
|
At
O.D. surface of bigger size flange after Lot No. /
Flange /Inspector’s punch |
|
| |
|
|
| 4
|
Punch last 4 digits of set no. on the
fabricated items after identification no. punch
|
Sub
Contractor |
| |
|
|
| 5
|
Punch clients part no.,if it is there on
the fabricated items as follows |
Sub
Contractor |
| |
For
Pipe |
:
|
Below pipe code no. |
|
| |
For
Tee |
:
|
Below pipe code no. on main body |
|
| |
For
Elbow/ Reducer |
:
|
Below forging lot no./ pipe code no. |
|
| |
For
Instrument Tee |
:
|
Below pipe code no. at branch body |
|
| |
|
|
| 6
|
Fill Traceability report for fabricated
items |
Sub
Contractor |
| |
|
|
|
|
|
|
|
|
|
|